Civil Works

Pcc works in progress at SP 171 to SP 176, rebar installed at SP 173 & 174 of PL.
Pcc works in progress at SP 171 to SP 176, rebar installed at SP 173 & 174 of PL.
Rebar cutting and bending at site
Rebar cutting and bending at site
Foundation excavation works in progress at SP 164,165, 166, 167, 168, 169, 170 and AB 40, 41&42 , SP almost completed and AB to be continuous
Foundation excavation works in progress at SP 164,165, 166, 167, 168, 169, 170 and AB 40, 41&42 , SP almost completed and AB to be continuous
Rebar cutting and bending work in progress for SP of PL.
Rebar cutting and bending work in progress for SP of PL.
Foundation works in progress
Foundation works in progress
Foundation works in progress
Foundation works in progress
Foundation excavation work in progress at SP 172,173,174,175,176 & 177 of PL.
Foundation excavation work in progress at SP 172,173,174,175,176 & 177 of PL.
SP & AB layout works in progress SP165 to SP173 an AB41 &AB42.
SP & AB layout works in progress SP165 to SP173 an AB41 &AB42.
Foundation excavation work in progress at SP 176 & 177 of PL
Foundation excavation work in progress at SP 176 & 177 of PL